Making decent progress on the 3000 GT. Main Hoop & Laterals, along with the windshield brace, roof bar and associated gussets are all complete. Rear hoop braces and 2/3's of the rear triangulation are complete with the third bar to be completed before the diagonal/harness bar goes in. Doorbar X's and sill bars are being fit and will be one with the cage shortly. Windshield will be coming out tomorrow to get ready for some of the gusseting into the A pillars and roof.
The always "fun" 7th & 8th points will be starting this evening. They'll be tying into the factory front framerails although not going through the firewall.
Some photos:
http://www.flickr.com/photos/23583304@N00/sets/72157604145725225/show/
The Neon looks like it's going to be ready for the St. Louis Regions first race of the season at GIR in 2 weeks. Interior and Cage paint is done, graphics installed, alignment done and all that other stuff that seemed to take forever. Sounds like tech inspection is going to happen this weekend! We'll be doing the GIR Test and Tune on Friday and playing around with some of our new toys.